Graph TheoryMediumGraph Algorithms
Graph Algorithms · Medium problem
A project has tasks with durations (days) and prerequisites (), (), (), (), (), (), (). Each listed number is how many days that task itself takes, and a task can only start once ALL of its prerequisites are finished. What is the earliest the whole project (ending at ) can finish, counting from day ?