A project's activities are arcs in a directed network from start event 11 to finish event 77: 1→2:4,1→3:2,2→4:5,3→4:3,3→5:6,4→6:2,5→6:4,6→7:31\to2{:}4, 1\to3{:}2, 2\to4{:}5, 3\to4{:}3, 3\to5{:}6, 4\to6{:}2, 5\to6{:}4, 6\to7{:}3 (days). Every activity leaving an event can start only once ALL activities entering that event are finished. What is the minimum number of days to complete the whole project?