Graph TheoryEasyGraph Algorithms
Graph Algorithms · Easy problem
A project has tasks with durations (days) and prerequisites ( days), ( days), ( days), ( days). Task can only start once ALL of its prerequisite tasks are finished. What is the earliest day can be completed, counting from day ?