Graph Algorithms · Easy problem

A project has tasks s,t,u,vs,t,u,v with durations (days) and prerequisites s→ts \to t (33 days), s→us \to u (22 days), t→vt \to v (44 days), u→vu \to v (55 days). Task vv can only start once ALL of its prerequisite tasks are finished. What is the earliest day vv can be completed, counting from day 00?